Crown Point Equity · HyperEdge · Indicative delivery schedule · as of 16 Nov 2026

HyperEdge Delivery Schedule

Ready for service

By site

Tracks and milestones

Delivery plan Agreement or document Management estimate Management decision Confirmed RFS Target RFS In-design RFS
Milestone detail
Select any milestone to see its timing and source.

Beyond the timeline

  • China Hall expansion: from about 40 MW gross toward about 120 MW gross through the gas lateral build and permanent generation, pending final site design (from 2028).
  • Dresden Phase 2: approximately 50 MW gross, extending toward 60 MW on full interconnection, scheduled for September 2028 after transformer delivery in April 2028 (not in the base case).

Indicative schedule, subject to definitive agreements and permits. Capacity figures are from the CPE delivery plan (14 Oct 2026); client milestone dates are management targets (20 Oct 2026); generator, unit delivery and commissioning timing follows the technical lead review of 19 Oct 2026. Ready-for-service (RFS) quarters are shown as a bronze band across the quarter on each site; quarter-level items span the whole quarter. RFS quarters at Dresden and Columbus are management targets (16 Nov 2026), subject to the NVIDIA platform selected and fixed in each site order; Pittsburgh is confirmed by management for Q3/Q4 2027; China Hall is in design. MW are gross; IT load figures are approximate and are fixed in each site order. Technical due diligence at each site includes a four-week window for Armada and customer design requirements (layout, test fit, power and cooling basis) and a site visit. At every site, rental or on-site generation and the modular units are on site two months before RFS, followed by two months of integration, QA and commissioning. At Dresden and Columbus, the on-site power partner performs or engages the electrical, interconnection and civil works. Pittsburgh and China Hall are powered initially by rental gas generators on trucked LNG, moving to owned engines and pipeline gas. Modular capacity is supplied by Armada.